P-201 / Commercial / Portside

Harbour Tower

Client
Portside Estates
Value
$94M
Duration
26 months
Handover
2 weeks early

Fig. 02 — South elevation, 1:500

Fig. 03 — Structure model

The brief

Portside Estates wanted a flagship office building on a tight harbour plot: soft ground, a live road on two sides and a deadline tied to an anchor tenant’s lease.

The challenge

  • Reclaimed land with groundwater two metres below the surface
  • No space for material storage on site
  • Traffic and noise limits from the port authority

Our solution

We designed a piled raft foundation with a secant-pile wall, prefabricated the steel frame off-site and delivered it just-in-time at night. A digital twin of the building tracked every element from factory to final bolt.

Two weeks early. Zero lost-time incidents. 310 people on site at peak.

Results

  1. Handed over 14 days ahead of programme
  2. 3.2% under the agreed budget
  3. 94% of site waste recycled