Off-site steel: what it saves (and what it doesn’t)
By Jon Akers · 27 Oct 2026
On Harbour Tower we prefabricated 2,900 tonnes of steel in a factory 60 km away and delivered it to site at night, in the exact order the crane needed it. It took 11 weeks off the programme. It also cost more up front.
What it saves
- Time: floors went up every 9 days instead of 14.
- Space: no laydown area on a site with none to spare.
- Safety: 60% fewer hours working at height.
The steel arrived in the order the crane needed it. Nothing waited on site.
What it costs
Design has to be frozen earlier, and transport adds around 4% to the steel package. If the client changes the layout late, off-site loses most of its advantage.
When it makes sense
- Tight urban sites with no storage space
- Repetitive floor plates (offices, hotels, housing)
- Programmes where every week of rent matters